|
Reactor
Decommissioning
History Overview Big Rock Point was a commercial BWR power reactor. It had a generating capacity of 67 MWe and operated from December 1962 to August 1997. Full power days not known. The reactor was 11-foot 4-inches (3.4-meter) diameter at the vessel flange x 30-foot (9.1-meter) tall. Principally fabricated from steel it weighed 109 Te empty and without the head. Reactor decommissioning, removal and transportation to Barnwell, SC was completed by October 2003. Reactor Decommissioning
Specifics Internals Removal Reactor Vessel Removal Prior to removal MOTA, using MDM (Metal Disintegration Machining from PCI), Diamond Wire (Cutting Edge), and Clam Shell cutters disconnected and capped all the water, steam and control rod drive pipes/tubes that ranged from 3-inch to 20-inch (76mm to 508mm) diameter to isolate the RV in preparation for removal. The removal of the RV was overseen by MOTA and supported by Barnhart Crane and Rigging out of Memphis, TN. Once the RV was placed into the shipping container the TCP was welded to the container to form the containment and provide the mechanical robustness necessary to meet demands of the 10CFR Pt 71 Hypothetical Accident Conditions (HAC). The weld had a special 'J' weld profile developed and implemented by PCI and required over 500 kg of filler material to complete taking 6 days of around the clock working. Once the welding was completed and successfully NDE'ed the internal void of the RV was grouted with low density cellular concrete (LDCC) through injection ports in the TCP. The LDCC was to exacting density and had to be poured in 'lifts' with laboratory analysis conducted between lifts to ensure that the exacting specifications were being met. Once the RV internals were grouted, the ports were welded shut and Barnhart lowered the loaded container onto its side to enable the annulus region between the inside of the container and the RV to be grouted also. Once grouted and the injection ports welded closed the complete package, total weight 266 Te, was carefully slid out of the containment sphere on hydraulic slide rails, lifted and placed onto a 36 axle Goldhofer trailer. Once all the tie-downs where in place and approvals received at 3:00 am, a briefing was held with the local, state authorities, the NRC and other interested parties and the shipment commenced. Taking (2) days and (2) 1000hp tractor units supplied by Barnhart the package reached a pre prepared rail siding some (52) miles away. With the Mammoet provided rail car, ETMX-1001 waiting, the package was carefully slid from the Goldhofer onto the ETMX-1001. The tie downs were secured, inspections made and then the 1400 mile rail journey commenced. After (8) days and numerous states the package safely arrived in Barnwell, SC for its final short road trip prior to burial. This was completed safely and without incident in late October 2003. The reactor head was shipped separately to EoU in a custom designed shipping container by Duratek in 2002. Segmentation
and Packaging Plan (S&P Plan) Key People
Contractors Comments Related Publications and Documents
References
|
|||||||||||||