Reactor Dismantlement History - USA only
Power, Test, and Research Reactors Scheduled for Dismantlement
revised 15 February 2015

The below table lists reactors that are closed and also reactors that are planned on being closed in near future.

Plant/Facility currently closed
Estimated Start of Reactor Disassembly
Comments
Crystal River 3 - a single 860 MWe B&W PWR.
2064
As of Dec 2013, Duke says SAFSTOR for 60-years, D&D complete 2074.
Dresden-1 is a 210 MWe GE BWR
2029-2031 (NRC web page)
No significant dismantlement reactor related is underway (SFP is decommissioned). DP approved 1993. To be dismantled with units 2 and 3 (they are licensed until 2031). Was closed in 1978
GE-VBWR (Vallecitos)
closure estimated 2019
No plans for significant dismantlement in the foreseeable future.
Indian Point 1 - a 275 MWe PWR
unknown
Plans are for D&D to be done with Unit-2. NRC web site says 2026. Has been closed since 1974.
Kewaunee - 570 MWe (W) PWR
after 2050
Fuel will be put in an ISFSI by 2020. Reactor work after 2050.
Oyster Creek - a 650 MWe GE BWR
unknown
Closure planned for 2019.
Peach Bottom 1 - helium cooled / graphite 40 MWe design
unknown
Plans are for D&D to be done with Units 2 and 3 due for shutdown (licenses expires in 2033/2034).
San Onofre 2/3 (SONGS-2 & 3)
RVI segmentation planned 2015-2019.
As of 9/23/14, "it is likely" (SCE) that the RV's will be segmented.
Vallecitos (see GE-VBWR)
See above
Because the NRC calls this facility "GE-VBWR" we list it the same. See "GE-VBWR" for this facility.
Vermont Yankee - a single 500 MWe GE BWR
unknown
The state is wanting commitment for an early and full decommissioning.

The below table lists reactors that could be announcing a closure date soon. This listing is based on recent announcements or publications that have creditability to them.

Plant/Facility pending closure
Estimated Start of Reactor Disassembly
Comments
Clinton - a single 1000 MWe GE BWR
unknown
Feb 2014: Exelon CEO Christopher Crane: "...We will be obligated to shut units down...". Industry tags Clinton and Quad Cities most probable.
Indian Point 2 & 3 - 1000 MWe (w) PWR
unknown
Sep 2013: Unit 2 is in it's "Period of Extended Operation" (PEO) while waiting for license extension approval. NYC mayor is wanting both remaining units to shut down.
Palisades - a single 800 MWe CE PWR
unknown
A July 2013 report by Mark Cooper noted that a 2017 closure could happen because of "brittle" metal around the reactor.
Quad Cities - qty 2 850 MWe GE BWR
unknown
Feb 2014: Exelon warns they may shut down low/no profit plants. Industry tags Clinton and Quad Cities most probable.

The purpose of this information is to provide the reader with an overview of when reactor disassembly activities are to begin at various USA nuclear facilities. Some of these facilities may have started the decommissioning process, but their reactor work has not been started. Our priority is on PWR's and BWR's in the United States; "swimming pool" type reactors generally will not be listed here. We will add non-USA facilities if we are provided with the information.

Please advise us of any errors or questionable information and we will immediately remove it or list our source to verify it is correct. We document our sources and references used and strive for 100% accuracy, however dates and other details can change over time. Please contact us before using any of our information displayed on any of our web pages.