Reactor Decommissioning History
Shoreham
revised 19 October 2014

Overview

Shoreham was a commercial BWR power reactor. It had a generating capacity of 820 MWe and 2436 MWt. It was operated briefly in 1989. It ran for two (or less) full power days. Reactor decommissioning took place in 1992. The reactor size was approximately 18-foot (5.5-meters) diameter with a wall thickness of 6.7-inches (170mm). Material was carbon steel with a stainless steel cladding on the inside.

Reactor Decommissioning Specifics

Internals Removal
All work was performed underwater. Thermal cutting was primarily used. Some long handle tools were also used for mechanical work such as unbolting and manipulating. All work on the internals was done remotely. All work on the internals was done by PCI Energy Services.

Reactor Vessel Removal
The reactor pressure vessel was cut dry by Wachs Technical Services. The vessel was cut into ring sections by mechanical (turning). Hydraulic powered drills were used to cut the required 6-inch (152mm) diameter lifting holes. Once the 18-foot (5.5-meters) diameter rings were lifted out of the vessel cavity they were placed into a secondary cutting area. They were size reduced into 3 or 4 arc segments using track mounted thermal (oxy-fuel) cutting.

Segmentation and Packaging Plan (S&P Plan)
Pre-site (internals): PCI Energy Services?
At site (internals): PCI Energy Services?


Pre-site (reactor vessel): Wachs Technical Services?
At site (reactor vessel): Wachs Technical Services?

Key People
Dan Hirsh was the on-site Project Manager for PCI Energy Services.
Al Solano was the on-site Project Manager for Wachs Technical Services.

Contractors
PCI Energy Services.
Wachs Technical Services (WTS).
Trentec (diamond wire cutting of the vessel bioshield)

Comments
Shoreham was a sister plant to Millstone-1.

Related Publications and Documents
No published technical papers have been found relating to the decommissioning of this reactor or segmentation of the reactor internals.

References
NRC's "Fact Sheet on Decommissioning Nuclear Power Plants" (web page 8/15/05).
TLG Services' web page 8/14/05
.
Nukeworker's web page as of 9/7/04.

Wachs Technical Services' web page as of 7/7/05.
Trentec's web page as of 8/15/05.

Click here to return to the Reactor Decommissioning History main page.