Reactor
Decommissioning
History
Fermi Unit-1
revised 14-FEB-2014
Overview
Enrico Fermi Unit 1 was a sodium cooled fast breeder
power reactor. Over the years it had a U.S. Supreme Court ruling, a fuel
melting incident, repair and recovery, and upgraded in output capacity.
It achieved a generating capacity of 200 MWt and operated from August
1963 to September 1972. Full power days was less than 60 days (this has
not been confirmed). The reactor was 14.5-feet (4.4-meter)
maximum diameter x 36.3-feet (11-meter) tall. Unit 2 is on the
same site and was operating during all decommissioning work to date.
Reactor Decommissioning
Specifics
Internals Removal
Internals removed by mechanical cutting (rotary saw blade). Laminated
plates made cutting difficult. This reactor is more complex than traditional
(Zion, Crystal River 3, SONGS, Rancho-Seco, etc.) commercial power reactors.
It has many more "Internals". With a few exceptions the internals
were Class A waste.
Reactor Vessel Removal
Mechanical cutting was used to cut the vessel
and "chambers" into sections. Work stopped in 2011/2012 before
vessel removal was complete. Although some size reduction was performed,
this cannot be called a true "segmentation". The lower reactor
vessel was 9.5-feet diameter x 21-feet tall. However, it was part of a
larger "vessel". This made removal in one piece of only the
"lower" vessel a possibility (and still an option). The large
vessel was surrounded by graphite blocks and a steel shielding structure.
Segmentation
and Packaging Plan (S&P Plan)
Unknown
Key People
Lynne Goodman, Fermi-1 Manager.
Dan Breiding, Decommissioning Project Coordinator Fermi-1.
Contractors
Energy Solutions
Siempelkamp Nuclear Services, Inc. (SNS) for the reactor work.
Comments
Work stopped before completion of scope. It may be shipped off-site in
large sections, but a final determination may not yet be decided. One
source says that the Internals are grouted and preparing for intact removal,
but that is questionable (we will effort for better details). Lessons
learned from Fermi-1 mechanical cutting was applied to tool design for
the RVI tools used at Zion.
Related Publications and Documents
Information on the actual work done will be listed
here as they become available.
References
"Fermi-1 Chronology" available
from Fermi-1 in early 2005.
A
brief Fermi-1 overview that was available from Fermi-1 in early 2005.
Conversations with SNS March 2011 through Feb 2012.
NRC web page 8/15/05.
NRC
web page 2/22/10.
Click here
to return to the Reactor Decommissioning History main page.
|