Reactor
Decommissioning
History
Connecticut Yankee (Haddam Neck)
revised 14-FEB-2014
Overview
Connecticut Yankee (called Haddam Neck by the NRC
and others) was a Westinghouse design commercial PWR power reactor. It
had a generating capacity of 1825 MWt and 590 MWe. It operated from 1967
(or 1968) to July 1996. Decommissioning began 1999 and the reactor removed
from site in 2003.
Reactor Decommissioning
Specifics
Internals Removal
All work was performed underwater. Abrasive Water Jet (AWJ) and Metal
Disintegration Machining (MDM) were primarily used. Some long handle tools
were also used for mechanical work such as unbolting and manipulating.
The AWJ was used to remove larger components (such as the Baffle Plates)
and to size reduce them for packaging. Several MDM tools were used to
help remove components (such as removing bolt heads). All work on the
internals was done remotely. All work on the internals was done by PCI
Energy Services.
Reactor Vessel Removal
The reactor pressure vessel was removed whole. This assembly was shipped
off-site via barge. It is not known which company cut the piping to free
the reactor vessel. Bigge Power Constructors provided the rigging services.
Segmentation
and Packaging Plan (S&P Plan)
Pre-site: PCI Energy Services; Steve
Larson, Jim Jesko, George Knetl, Fred
Frank.
At
site: PCI Energy Services?
GTCC
Packaging
The
Greater than Class C (GTCC) material from the reactor will remain on site
with the fuel in the ISFSI. There are three NAC MPC canisters.
Key People
Jim Jesko was the on-site Project Manager for PCI Energy
Services.
Contractors
Bechtel Power Corporation.
Bigge Power Constructors.
PCI Energy Services.
Comments
This was the first of three underwater internals segmentations done in
the USA using Abrasive Water Jet (AWJ) as the primary cutting tool (CY,
SONGS-1, and Maine Yankee). AWJ was used (dry; not underwater) at Trojan
for a repair project before this. It is believed that AWJ was used in
Japan on reactor internals before being used at CY. AWJ is planned to
segment the Rancho Seco RV dry (i.e. not underwater).
Although AWJ is preferred over Plasma from an ALARA standpoint,
it generates a lot of secondary waste. The cutting media (garnet) is very
difficult to contain. The force of the abrasive is so great that it can
cut through containment devices 2-feet (600mm) away. If allowed to accumulate,
the abrasive will become similar to wet concrete. Because CY was the first
USA reactor to use this process, there were many lessons learned. The
two following AWJ segementations (SONGS-1 and Maine Yankee) saw important
changes to refine this process.
Related Publications and Documents
No published technical papers have been found relating
to the decommissioning of this reactor or segmentation of the reactor
internals.
References
NRC's
"Fact Sheet on Decommissioning Nuclear Power Plants" (web page
8/15/05).
Southern California Edison's web page as of 8/12/05.
Bigge Power Constructors' printed literature dated 8/25/04.
PCI Energy Services' web page 8/12/05.
Steve Larson interview 8/12/05.
Click here
to return to the Reactor Decommissioning History main page.
|