Recent Updates as of 8 June 2015
RVI
The
Reactor Vessel Internals removal from the vessel
is complete.
RV
Reactor Vessel segmentation is almost complete.
The bottom bowl is yet to be removed from the reactor cavity.
GTCC
The single GTCC can is in the ISFSI.
Overview
Humboldt Bay Unit 3 was a unique 63MWe BWR in Eureka,
California that was roughly
9-foot (2.7-meter) diameter x 31-foot (9.4-meter) tall. Commercial
operations was achieved in 1963. Final reactor operation was July 1976
when it was shut down because of seismic concerns. Because of economic
reasoning, it was decided in 1983 to decommission the unit. Units 1 and
2 were fossil fuel plants that were demolished while the Unit-3 Humboldt
Bay decommissioning work was beginning.
Reactor Decommissioning
Specifics
Internals Removal
The Reactor Vessel Internals (RVI) were much different and smaller than
traditional commercial power reactors (Zion, Crystal River 3, SONGS-1,
Rancho Seco, etc.). The
RVI were mechanically cut in-situ using fully remote tooling.
Siempelkamp Nuclear Services (SNS) did the work.
Reactor Vessel Removal
Mechanically cutting began in early 2014 by Siempelkamp
Nuclear Services (SNS). The vessel will be segmented and
packed into shipping containers as Class A waste.
Segmentation
and Packaging Plan (S&P Plan)
The first Humboldt
Bay decommissioning plan had the reactor vessel removed
and shipped off site whole. PG&E (around 2010) decided to look at
other options to avoid public concern of shipping on a waterway. The second
approach developed by EH Wachs in November of 2010 was to incrementally
lift and segment the RV (Westinghouse also provided a similar proposal).
This EH Wachs plan required hands-on removal of the outer insulation in
a very confined and high dose area. A third approach was proposed by Plant
Decommissioning (with Wachs Services) on 1/25/2011 that eliminated many
of the risks associated with the "lift and cut" plan. The Plant
Decommissioning (PD) "windowing" plan did not require lifting
of the vessel or removal of outer insulation (huge ALARA benefit). It
also allows for the option to utilize faster hands-on work when dose rates
allow it. In April 2011, PG&E developed the PD plan into the current
S&P Plan for the Reactor Vessel.
GTCC
Packaging
The
Greater than Class C (GTCC) material from the reactor will remain on site
with the fuel in the ISFSI. These are Holtec Hi-Star models. The on-site
ISFSI has the Fuel
stored in (5) dry casks along with (1) GTCC can
underground (below grade).
Key People
Kerry Rod (PG&E
D&D Project Manager).
Steve Larson (Window S&P plan and RV segmentation tool concepts).
Horst Kwech (Tool Design).
Al Solano (RV PM).
Contractors
PG&E is doing some of the work
and staffing.
EnergySolutions.
Siempelkamp Nuclear Services, Inc.
(SNS) doing RVI and RV segmentation.
Wachs Energy Services (steam condenser segmentation).
Comments
PG&E was planning on shipping the RPV off-site
as one piece. However, this was abandoned for segmenting. Obviously there
would be public concern of a nuclear vessel floating under the Golden
Gate bridge. But also possibly because
of the problems encountered when
planning on shipping the SONGS-1 RV off-site.
Related Publications and Documents
"Dry Cask Storage Pacific Gas
& Electric – Humboldt Bay Power Plant - 10217" from WM2010 Conference,
March 7-11, 2010.
References
Wikipedia web page as of Feb 22,
2010.
NRC web page from Feb 2010 to Feb 2012.
Conversations
with site people Jan 2010 through October 2014.